ROVER Non-Critical Notice

Notice ID: 50905
Notice Type: PSO
Critical: N
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2025-01-13 08:26:00.0
Subject: Rover 2025 Pipeline Outage and Maintenance Summary
Notice Effective Date/Time: 2025-01-13 08:26:00.0
Notice End Date/Time: 2200-01-01 00:00:00.0
Notice Text:

Updated as of

5/7/2025

 

Listed below is a summary of the planned outages that could affect capacity or impact any receipt/delivery locations during the Rover 2025 outage season.  This schedule is not a complete list of all outages and is subject to change as the season progresses to reflect any project delays, cancellations or additions.  Additionally, anticipated impact and restrictions are subject to change.  
*All scheduled dates represent gas days as defined in the Rover Tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

Start Date

End Date

Location

Unit(s)

Maintenance

Anticipated Impact

Meter(s) Impact

1/6/25

2/6/25

Wayne

202

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

1/6/25

1/6/25

Leesville

201

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

1/15/25

1/15/25

Sherwood

201

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

1/20/25

1/23/25

Leesville

204

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

1/28/25

1/28/25

Majorsville

203

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

1/29/25

1/31/25

Bulger

201

Preventative Maintenance

Capacity through Bulger station limited.  Meter subject to scheduling reductions.

70005

2/10/25

4/1/25

Crawford

201

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

2/10/25

4/1/25

Crawford

202

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

2/10/25

4/1/25

Crawford

203

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

2/11/25

2/14/25

Bulger

203

Preventative Maintenance

Capacity through Bulger station limited.  Meter subject to scheduling reductions.

70005

2/12/25

2/12/25

Sherwood

202

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

2/17/25

2/20/25

Leesville

203

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

2/18/25

2/18/25

Majorsville

202

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

2/26/25

2/27/25

Leesville

202

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

3/4/25

3/4/25

Majorsville

202

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

3/5/25

3/5/25

Majorsville

201

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

3/6/25

3/6/25

Wick

Meter Station

Replace Meter Run

Capacity through Wick Meter Station limited.  Meter subject to scheduling reductions.

70045

3/11/25

3/11/25

Sherwood

203

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

3/19/25

3/19/25

Bulger

Station

Tie in for Instrument Air

Capacity through Bulger station limited.  Meter subject to scheduling reductions.

70005

3/26/25

3/26/25

Wayne

202

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

3/27/25

3/28/25

Leesville

201

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

4/2/25

4/2/25

Majorsville

Station

ESD

Capacity through Majorsville Station Limited.  Meter subject to scheduling reductions.

70004

4/2/25

4/2/25

Leesville

Station

ESD and Fuel Skid Piping Upgrade

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

4/7/25

5/8/25

Bulger

202

Overhaul

Capacity through Bulger station limited.  Meter subject to scheduling reductions.

70005

4/8/25

4/11/25

Wayne

203

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

4/7/25

4/7/25

Sherwood

201

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

4/7/25

4/7/25

Sherwood

202

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

4/8/25

4/8/25

Sherwood

203

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

4/9/25

4/9/25

Sherwood

Station

ESD and Install Ball Valves

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

4/15/25

4/15/25

Majorsville

202

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

4/16/25

4/16/25

Clarington

Station

Install Valves

Capacity through Clarington Station limited. Meter subject to scheduling reductions.

70011

4/22/25

4/22/25

Crawford

201-203

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

4/29/25

4/29/25

Sherwood

201

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

4/30/25

4/30/25

Sherwood

202

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

5/1/25

5/1/25

Sherwood

203

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

5/6/25

5/7/25

Sherwood

201

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

5/6/25

5/9/25

Wayne

201

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

5/13/25

5/16/25

Sherwood

201

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

5/13/25

5/13/25

Crawford

202

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

5/14/25

5/14/25

Crawford

201

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

5/15/25

5/15/25

Crawford

203

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

5/20/25

5/22/25

Majorsville

201

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

6/3/25

6/5/25

Sherwood

202

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

6/10/25

6/13/25

Sherwood

202

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

6/10/25

6/10/25

Crawford

201

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

6/11/25

6/11/25

Crawford

202

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

6/12/25

6/12/25

Crawford

203

Preventative Maintenance

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

6/16/25

6/27/25

Wayne

206

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

6/17/25

6/17/25

Majorsville

203

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

7/1/25

7/1/25

Majorsville

202

Preventative Maintenance

Capacity through Majorsville station limited.  Meter subject to scheduling reductions.

70004

7/7/25

7/18/25

Wayne

204

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

7/8/25

7/10/25

Sherwood

203

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

7/15/25

7/18/25

Sherwood

203

Preventative Maintenance

Capacity through Sherwood station limited.  Meter subject to scheduling reductions.

70001

8/11/25

8/22/25

Wayne

205

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

8/13/25

8/13/25

Seneca

Station

ESD

Capacity through Seneca Station Limited. Meters subject to scheduling reductions.

70002, 70016, 70012

8/20/25

8/20/25

Clarington

Station

ESD

Capacity through Clarington Station limited. Meter subject to scheduling reductions.

70011

9/15/25

9/26/25

Crawford

204

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited

10/13/25

10/24/25

Crawford

205

Overhaul

Mainline capacity may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

All customers Mainline capacity limited