Notice Text:

Revision (Y/N)

Start Date

End Date

Prev Start Date

Prev End  Date

 Facility

Zone

Line Segment  OP Area

Maintenance

Potential Impact *

OA or News

N

3/11/2025

3/12/2025

 

 

Alto Station

Zone 1

Gulf Run

Semi-Annual Maintenance

8

51672

N

3/20/2025

3/21/2025

 

 

Panola Station

Zone 1

Gulf Run

Semi-Annual Maintenance

7

Required

Y

4/1/2025

4/5/2025

3/25/2025

3/28/2025

Westdale Station

Zone 1

Gulf Run

Units 1, 2 Semi-Annual Maintenance

8

Required

N

4/3/2025

4/3/2025

 

 

Line CP (BOL to Panola)

Zone 1

Gulf Run

Cleaning Pig

1

N/A

N

4/4/2025

4/4/2025

 

 

Line CP (Panola to Westdale)

Zone 1

Gulf Run

SCP Cleaning Pig

1

TBD

N

4/5/2025

4/5/2025

 

 

Line CP (Westdale to Vernon)

Zone 1

Gulf Run

SCP Cleaning Pig

1

TBD

N

4/6/2025

4/6/2025

 

 

Line CP (Vernon to Delhi)

Zone 1

Gulf Run

SCP Cleaning Pig

1

TBD

N

4/8/2025

4/15/2025

 

 

Vernon Station

Zone 1

Gulf Run

Units 1, 2, 3 Semi-Annual Maintenance

8

Required

N

May TBD

May TBD

 

 

Panola Station

Zone 1

Gulf Run

Unit 2 Replacement

6

TBD

1.  No capacity impact is expected at this time.

 

 

 

 

 

 

 

2.  Coordinating with necessary loads.

 

 

 

 

 

 

 

3.  Based on historical and current throughput, no capacity impact is expected.  In the event nominations increase significantly, restrictions may become necessary.

 

4.  Coordinating maintenance with interconnecting pipe to minimize customer impact.  No capacity impact is expected at this time; however, if operating conditions change, affected parties will be notified.

5.  Affected production notified of shut-in during work.

 

6.  Customers may experience pressure fluctuations, but no capacity impact is anticipated.

 

 

 

 

 

7.  Based upon customer nominations, restrictions may become necessary.

 

8.  Based on all available information, capacity will be impacted.  Capacity reductions will be done in accordance with the provisions of EGT's tariff regarding scheduling and interruption of services.