GR Non-Critical Notice

Notice ID: 47029
Notice Type: PSO
Critical: N
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2024-08-19 10:26:00.0
Subject: Planned Service Outages [August 2024 Calendar]
Notice Effective Date/Time: 2024-08-19 10:26:00.0
Notice End Date/Time: 2200-01-01 00:00:00.0
Notice Text:

Revision (Y/N)

Start Date

End Date

Prev Start Date

Prev End  Date

 Facility

Zone

Line Segment  OP Area

Maintenance

Potential Impact *

OA or News

N

9/9/2024

9/9/2024

 

 

Line CP (Carthage to Panola)

Zone 1

South

Cleaning pig

6

N/A

N

9/10/2024

9/10/2024

Line CP (Panola to Westdale)

Zone 1

South

SCP Cleaning Pig

6

N/A

N

9/10/2024

9/11/2024

 

 

Delhi Station

Zone 1

South

Semi-annual maintenance

8

46646

N

9/11/2024

9/11/2024

 

 

Line CP (Westdale to Vernon)

Zone 1

South

SCP Cleaning Pig

6

N/A

N

9/12/2024

9/12/2024

Line CP (Vernon to Delhi)

Zone 1

South

SCP Cleaning Pig

6

N/A

N

9/12/2024

9/13/2024

 

 

Alto Station

Zone 1

South

Semi-annual maintenance

8

46789

N

9/12/2024

9/12/2024

Line CP (Kinderhawk IC)

Zone 1

South

OPP Testing

8

20240808

N

9/13/2024

9/13/2024

Gulf Run (Westdale to DeRidder)

Zone 1

South

Cleaning pig

3

N/A

N

9/14/2024

9/14/2024

 

 

Gulf Run (DeRidder to Bienville)

Zone 1

South

Cleaning pig

3

N/A

N

9/17/2024

9/20/2024

Panola Station

Zone 1

South

Units 2, 3 - Semi-annual maintenance (one at a time)

8

N/A

N

11/5/2024

11/9/2024

 

 

Vernon Station

Zone 1

South

Standby generator and electric starters install

8

Required

1.  No capacity impact is expected at this time.

 

 

 

 

 

 

 

2.  Coordinating with necessary loads.

 

 

 

 

 

 

 

 

3.  Based on historical and current throughput, no capacity impact is expected.  In the event nominations increase significantly, restrictions may become necessary.

 

4.  Coordinating maintenance with interconnecting pipe to minimize customer impact.  No capacity impact is expected at this time; however, if operating conditions change, affected parties will be notified.

 

5.  Affected production notified of shut-in during work.

 

6.  Customers may experience pressure fluctuations, but no capacity impact is anticipated.

 

 

 

 

 

7.  Based upon customer nominations, restrictions may become necessary.

 

8.  Based on all available information, capacity will be impacted.  Capacity reductions will be done in accordance with the provisions of EGT's tariff regarding scheduling and interruption of services.