Notice Text:

Revision (Y/N)

Start Date

End Date

Prev Start Date

Prev End  Date

 Facility

Pooling Area

Zone

Maintenance

Potential Impact *

N

3/12/2024

3/13/2024

 

 

Delhi Station

Perryville

Zone 1

Semi-annual maintenance

8

N

3/14/2024

3/15/2024

Alto Station

Perryville

Zone 1

Semi-annual maintenance

8

N

 3/19/24

3/22/2024

 

 

Vernon Station

Haynesville

Zone 1

Unit 1, 2 - Semi-annual maintenance (one at a time)

8

N

3/26/2024

3/27/2024

Vernon Station

Haynesville

Zone 1

Unit 3 - Semi-annual maintenance

8

N

4/2/2024

4/5/2024

 

 

Panola Station

Carthage

Zone 1

Station ESD / Unit 2 Semi-annual maintenance

8

N

4/9/2024

4/9/2024

Westdale Station

Starks

Zone 2

Station ESD

1

 

 

1.  No capacity impact is expected at this time.

2.  Coordinating with necessary loads.

3.  Based on historical and current throughput, no capacity impact is expected.  In the event nominations increase significantly, restrictions may become necessary.

4.  Coordinating maintenance with interconnecting pipe to minimize customer impact.  No capacity impact is expected at this time; however, if operating conditions change, affected parties will be notified.

5.  Affected production notified of shut-in during work.

6.  Customers may experience pressure fluctuations, but no capacity impact is anticipated.

7.  Based upon customer nominations, restrictions may become necessary.

8.  Based on all available information, capacity will be impacted.  Capacity reductions will be done in accordance with the provisions of EGT's tariff regarding scheduling and interruption of services.