Date Requested: Oct 18 2024 4:20 AM
FGT Non-Critical Notices
TSP Name: Florida Gas Transmission (TSP: 006924518)
Notice Type | Posted Date/Time | Notice Eff Date/Time | Notice End Date/Time | Notice ID | Subject | Response Date/Time |
---|---|---|---|---|---|---|
Cap. Constraint | Oct 17 2024 7:30PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48813 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 17 2024 6:29PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48812 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 17 2024 6:29PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48811 | CS #9 Franklinton | |
Cap. Constraint | Oct 17 2024 3:02PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48810 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48809 | Tres Palacios Storage (Rec) | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48807 | GSPL Merrill | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48808 | Lake Murphy-TECO/PGS | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48803 | East Leg Group | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48804 | CS #9 Franklinton | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48805 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 17 2024 2:02PM | Oct 18 2024 9:00AM | Oct 19 2024 8:59AM | 48806 | Jacksonville Reticulated Area-Segmented | |
Cap. Constraint | Oct 17 2024 10:35AM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48802 | Jacksonville Reticulated Area-Segmented | |
Cap. Constraint | Oct 17 2024 10:35AM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48801 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 16 2024 6:32PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48796 | CS #9 Franklinton | |
Cap. Constraint | Oct 16 2024 6:32PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48797 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 16 2024 6:32PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48798 | Tres Palacios Storage (Rec) | |
Cap. Constraint | Oct 16 2024 6:32PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48795 | CS #7 Eunice Zone 1 | |
Other | Oct 16 2024 4:01PM | Oct 16 2024 4:01PM | Nov 1 2024 5:00PM | 48789 | ETIH South Mississippi Project Open Season | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48783 | CS #8 Zachary Zone 2 | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48784 | Jacksonville Reticulated Area-Segmented | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48785 | Lake Murphy-TECO/PGS | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48786 | Tres Palacios Storage (Rec) | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48780 | East Leg Group | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48781 | CS #7 Eunice Zone 1 | |
Cap. Constraint | Oct 16 2024 1:39PM | Oct 17 2024 9:00AM | Oct 18 2024 8:59AM | 48782 | CS #9 Franklinton | |
Other | Dec 11 2023 3:57PM | Dec 11 2023 3:57PM | Jan 1 2025 12:00AM | 41090 | FGT 2024 Holiday Schedule for Capacity Release | |
Other | Aug 28 2023 9:00AM | Aug 28 2023 9:00AM | Jan 1 2200 12:00AM | 38331 | ROFR Bids Posting for FTS-1 Capacity | |
Other | Aug 28 2023 9:00AM | Aug 28 2023 9:00AM | Jan 1 2200 12:00AM | 38332 | ROFR Bids Posting for FTS-1 Capacity | |
Other | Nov 28 2022 10:45AM | Nov 28 2022 10:45AM | Jan 1 2200 11:59PM | 31891 | Methane Charge | |
Other | Apr 2 2018 4:38PM | Apr 2 2018 4:38PM | Until further notice | 13492 | EDI Available | |
Other | Jan 30 2018 1:17PM | Jan 30 2018 1:17PM | Until further notice | 13182 | FGT East Leg Point List Updated 2018-01-30 | |
Other | Jan 24 2017 3:44PM | Jan 24 2017 3:35PM | Until further notice | 11331 | FGT West Leg Point List Updated 2017-01-24 | |
Other | May 25 2016 10:35AM | May 25 2016 10:32AM | Until further notice | 9890 | Flow Day Diversion Confirmation Changes Effective June 1, 2016 | |
Other | Mar 26 2015 9:52AM | Mar 26 2015 9:00AM | Until further notice | 9227 | FERC Order 801 Compliance | |
Gas Quality | Feb 6 2015 3:30PM | Feb 6 2015 3:29PM | Until further notice | 9226 | Gas Quality - Wobbe Index | |
Gas Quality | Feb 6 2015 3:29PM | Feb 6 2015 3:27PM | Until further notice | 9225 | Gas Quality - CO2 | |
Other | Sep 9 2014 11:06AM | Sep 9 2014 11:04AM | Until further notice | 9220 | FGT Flow Day Diversion Updates | |